No, it shows the same error "Create cost element..."
Settling the 2 lines to the same P&L account doesn't work because one source requires a cost element and the other source rejects it.
But I tried to create a copy of 800 account, created a cost element for it, and used it for the revenue line. Only then the revenue source will settle --> but it re-posts that revenue to the project again during the settlement.